Blasting through rock in Rossland
CITY OF ROSSLAND
Contractors had to blast through 240 linear feet of bedrock to accommodate new sewer, water and stormwater lines during a Rossland, B.C. infrastructure project.
Blasting through solid bedrock to make room for sewer and watermains was one of the challenges of a recent roadbuilding project in the West Kootenays.
Rossland, B.C. decided to move forward with the utility work after accepting an offer from the B.C. Ministry of Transportation to fund a downtown paving project.
The 60-year-old sewer system is being replaced due to its condition and capacity, said Darrin Albo, manager of operations, city of Rossland.
“We’ve had some major back-ups in some of the commercial buildings downtown, and when we did some camera inspection work, we realized the lines were in worse shape than we had originally thought.”
The city’s water infrastructure dates back even further, with some of the lines estimated at more than a century old.
Construction of the original sewer line required blasting down to 17 feet in some spots to create the proper incline for a gravity-fed sewer system.
“We can’t follow the original route for two reasons,” said Albo.
“It’s difficult to simultaneously excavate and replace a sewer line that’s buried that deep. Also, highway closure rules dictate that we need to keep at least one lane open on the road at any time, but the existing sewer line is located in the centre of the right of way. Digging it up and replacing it would close both lanes at the same time.”
The solution was to realign the new sewer line and move it closer to one side of the road.
While some bedrock was expected, its exact location was unknown.
Thorough core sampling couldn’t be conducted for fear of rupturing existing sewer and water lines with drills.
Once the roadbed was opened, it became clear that contractors would have to blast through 240 linear feet of bedrock to accommodate new sewer, water and stormwater lines.
Contractor Meka Construction Services conducted an extensive pre-blast inspection of local buildings to document any pre-existing cracks or blemishes.
The city then called on B & N Blasting Contractors Ltd. to remove the rock using explosive charges scheduled about three hours apart.
“The charges were placed in small holes, very close together, and the excavation was covered with rubber blast mats to damp the explosions,” said Albo.
“Incredibly, the blasting wasn’t much of an issue downtown. We were more concerned with creating an adequate number of temporary parking spaces behind some of the businesses and accommodating pedestrians.”
Blasts were monitored by seismic equipment to measure the magnitude and volume of explosions, although Rossland mayor Greg Granstrom compared the effect of the controlled blasts to the shock of a logging truck hitting a pothole at 50 km/h.
Shopping continued as usual a few minutes before and after each blast.
Regulations dictate that water lines may not occupy the same trench as a sewer line.
Once the deep sewer trench had been completed, the contractor turned around and blasted a second trench for potable water between the sewer trench and the sidewalk, this time to five to six feet below the surface of the road.
“While we were blasting, we came across a lot of old infrastructure dating as far back as the 1800s,” said Albo.
“That includes old water lines, some of which were live and some dead. At one point during an operation to remove rubble from the blasting we came across an underground crevice that some people thought might be an old mineshaft.”
While the crevice might have been excavated as a potential mine entrance, engineers determined that there was no shaft beyond it. The crevice was filled with five cubic metres of concrete.
“We hope to have the entire project finished and asphalt down on the roads by Dec. 1,” said Albo.
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
$1,000,000,000 Edmonton AB Prebid
$220,000,000 Medicine Hat AB Negotiated
AGRICULTURAL EXHIBITION EXPANSION
$50,000,000 Calgary AB Prebid
| CURRENT STORIES |
- Construction Site Arson
- Industry reacts to surprise B.C. Liberal majority
- Journal of Commerce Update for the week of May 20th, 2013
- Calgary Airport Tunnel
- Worker at centre of union sign up allegations speaks out
- Calgary program aims to get more people into the trades
- Midrise in the City
- Veterans battle barriers into the trades
- Government makes changes to online tendering
- SNC-Lavalin maintains that new bribery allegations have been resolved
- B.C. faces a tough battle for top talent
- Keyano College building state of the art training facility
- Essential skills can play a vital role in an apprentices' success
- Taking a closer look at the risks in green building for contractors
- Colleges conduct construction research in addition to teaching
- Skills Canada BC Competition
- Lower Mainland high school trades program is unique
- Construction Learning Forum aims to educate
- High schools looking for more industry participation
- Industrial construction supervisor program takes off
- Saskatchewan bill passed
- Edmonton garners support for regional cash for arena
- Feds pledge $5 million for Vimy memorial
- VIDEO: Competing in the trades
- Provinces need to loosen up apprenticeship rules
- Way Up on Westwood
- Building Up On Bayview
- Barrie Construction Association rolls with motorcycle ride for cancer
- Vimy Ridge memorial gets new visitor centre
- Minnesota Vikings unveil new multi-use stadium plan
- Proposed Ambassador Bridge twinning draws Windsor mayor’s ire
- Construction on pedestrian tunnel to Billy Bishop Airport continues to make progress
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More