Premier Greg Selinger is travelling to Manitoba's north to christen the province's newest hydroelectric project.
Manitoba Hydro spokesman Glenn Schneider said the first of the $1.6 billion Wuskwatim Dam’s three huge turbines began churning out power on June 22.
The 200-megawatt generating station on the Burntwood River, about 45 kilometres southwest of Thompson, has taken six years to build.
It was built to supply more power to Hydro’s northern customers and the domestic market.
Wuskwatim is the first hydroelectric project in which Manitoba Hydro has an aboriginal community as an equity partner.
Hydro and the Nisichawayasihk Cree Nation (NCN) have formed the Wuskwatim Power Limited Partnership, which owns the generating station.
“It’s a big deal for the water to hit the turbine blades,’’ Schneider said. “There’s a lot that could go wrong. You want to make sure all your electrical equipment is working right and that the mechanical aspects of it are good.’’
It’s estimated the dam’s profits will earn up to $40 million a year, when it’s fully operating, and the goal is for NCN to own 33 per cent of the dam.
NCN will use that money to build new houses and roads and send young people to school in southern Manitoba, among other things.
Hydro is using a similar process in building the $5.6 billion Keeyask generating station on the Lower Nelson River, a project more than twice the size of Wuskwatim. Hydro is working with four First Nations on a joint-ownership agreement.
Keeyask is to be built to export surplus power to Minnesota and Wisconsin.
Selinger’s trip to mark the Wuskwatim opening comes after Hydro’s export revenue forecast came in lower than previously anticipated. It’s expecting a $1 billion drop in export revenues over the next decade, compared to the last forecast, and a $4 billion drop over the next 20 years, compared to prior estimates.
The drop is blamed on the poor U.S. economy, lower export prices and an abundance of cheap natural gas.
Selinger and Hydro have said those market factors won’t last indefinitely and won’t delay the Keeyask construction – site preparation has already begun – nor the proposed $5 billion Conawapa generating station, also on the Lower Nelson River, and the new $3.28 billion Bipole III transmission line.
Hydro’s southern customer, Minnesota Power, is also planning ahead and recently submitted a proposal to build a 500-kilovolt line – more than double the load first planned – from the Manitoba border to Duluth, Minn., to deliver more Manitoba-made power to its customers.
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
$1,000,000,000 Edmonton AB Prebid
$220,000,000 Medicine Hat AB Negotiated
AGRICULTURAL EXHIBITION EXPANSION
$50,000,000 Calgary AB Prebid
| CURRENT STORIES |
- Construction Site Arson
- Journal of Commerce Update for the week of May 20th, 2013
- Industry reacts to surprise B.C. Liberal majority
- Calgary Airport Tunnel
- Worker at centre of union sign up allegations speaks out
- Calgary program aims to get more people into the trades
- Midrise in the City
- Veterans battle barriers into the trades
- Government makes changes to online tendering
- SNC-Lavalin maintains that new bribery allegations have been resolved
- B.C. faces a tough battle for top talent
- Keyano College building state of the art training facility
- Essential skills can play a vital role in an apprentices' success
- Taking a closer look at the risks in green building for contractors
- Colleges conduct construction research in addition to teaching
- Skills Canada BC Competition
- Lower Mainland high school trades program is unique
- Construction Learning Forum aims to educate
- High schools looking for more industry participation
- Industrial construction supervisor program takes off
- Saskatchewan bill passed
- Edmonton garners support for regional cash for arena
- Feds pledge $5 million for Vimy memorial
- VIDEO: Economic Update May 21, 2013
- VIDEO: Competing in the trades
- Multi-employer approach needed in apprenticeships
- New Perspective
- ACEC’s input helps develop global engineering guidelines
- Clerk of works position gives peace of mind on projects
- World Trade Center developer’s plan for a 926-foot tower moving ahead
- Call for action after MOL says workers are responsible for their own safety
- Cold spring and weak construction hurt Deere’s 2013 predictions
- CanBIM reschedule June session
- More green roofs top Toronto buildings
- Witness recants testimony in Montreal corruption case
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More