New process could extend the service life of busy roads
ONTARIO MINISTRY OF TRANSPORTATION
Ontario has approved options to bid asphalt cracking repairs using either a fibre Stress Absorbing Membrane Interlayer (SAMI) or a geotextile mat SAMI treatment process.
The Ontario Ministry of Transportation (MTO) has approved options to bid asphalt cracking repairs using either a fibre Stress Absorbing Membrane Interlayer (SAMI) or a geotextile mat SAMI treatment process, but says it is still investigating where it works best.
One of the biggest challenges the MTO faces in terms of road maintenance is reflective cracking, which most often happens over the joints of the underlying concrete slabs or where there are cracks in cement bound base layers.
Other causes include expansion, contraction and bending from temperature shift, traffic or where roads have been widened and there are different settlements of the substrate.
There are a couple of different ways of heading off the issue during construction and repair, including laying down asphalt reinforcement grids to add tensile stiffness, keeping cracks to a minimum and preventing water seepage to lower levels where freeze-thaw damage can be much more substantial.
The most common crack treatment has been rout and seal, but the application of a micro-surface is a better, though still, short-term solution because after a few seasons the cracks propagate through the surface again, defeating the overlay.
The MTO has also been testing the use of chopped fibreglass strands, five to 10 cm in length, as a SAMI application in combination with polymer-modified asphalt emulsion sprayed onto the pavement surface, similar to conventional chip seal coating.
After spraying fibre membrane, stone chip aggregate is laid before a final pavement overlay to allow construction vehicles to safely use it.
The SAMI acts as a waterproof membrane and helps delay reflective cracking and propagation by absorbing some of the pavement strain from vehicle loads.
This technique is common to many jurisdictions and has been in use in Europe for 30 years.
While other Canadian and North American jurisdictions have used it, the MTO trialed its first test of it with positive results on a 12.75 km section of Highway 62, near Madoc north of Belleville in 2009.
That sprayed-fibre application was with a specially designed trailer which laid material down in a four-metre-wide ribbon in 300 mm increments in which fiberglass strands were pneumatically inserted into the binder emulsion to ensure full immersion and random layering.
It required about 10 per cent more binder for the polymer-modified cationic rapid setting emulsion applied at rates varying between 1.6 and 2.0 lt/m2 depending on the size of the aggregate.
As a general rule, 10-per-cent more binder is applied to ensure proper encapsulation of the fibre.
Since then, the Highway 62 section is performing well, the MTO reports, with only minimal reflective cracks which is a positive because the pavement was highly distressed.
Other test sections have been built on Highway 41, south of Denbigh, and on Highway 17, east of Sturgeon Falls.
Like other asphalt emulsion applications, FiberMat should not be applied in cold damp conditions, said Todd Filson, a pavement design and evaluation officer at MTO’s geotechnical engineering office, noting like chip seal technology there are strict specifications around ambient temperatures and timelines.
While challenges remain, there are many positives, including cost.
“At a cost of $4.50 — $5.50 a square metre, without the need for additional shoulder material and other construction needs, the savings can be found in the initial application as well as extending the service life of the road,” Filson said.
“If proven successful over time, SAMI will be deemed a value-added tool in the ministry’s preservation management tool box and could be applied in other areas across the province.”
And, so far, it seems to be hitting all the right scores, he said.
Though, on high speed roads, special care aggregate selection, embedment and sweeping, to reduce the possibility of windshield damage from loose stone, must be taken.
“We don’t currently have any experience with SAMI on higher volume — freeway conditions though a trial on Highway 401 west of Kingston is planned for summer 2013,” he said.
ONTARIO MINISTRY OF TRANSPORTATION
| MOST POPULAR STORIES |
- Union threatens legal action over allegations of signing apprentices at BCIT
- New partnership to bid on Fort McMurray transmission project
- Industry reacts to surprise B.C. Liberal majority
- VIDEO: Transit-oriented development in Edmonton
- Labour federation takes issue with some political donations in Alberta
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
$1,000,000,000 Edmonton AB Prebid
$220,000,000 Medicine Hat AB Negotiated
AGRICULTURAL EXHIBITION EXPANSION
$50,000,000 Calgary AB Prebid
| CURRENT STORIES |
- Construction Site Arson
- Industry reacts to surprise B.C. Liberal majority
- Journal of Commerce Update for the week of May 20th, 2013
- Calgary Airport Tunnel
- Worker at centre of union sign up allegations speaks out
- Calgary program aims to get more people into the trades
- Midrise in the City
- Veterans battle barriers into the trades
- Government makes changes to online tendering
- SNC-Lavalin maintains that new bribery allegations have been resolved
- B.C. faces a tough battle for top talent
- Keyano College building state of the art training facility
- Essential skills can play a vital role in an apprentices' success
- Taking a closer look at the risks in green building for contractors
- Colleges conduct construction research in addition to teaching
- Skills Canada BC Competition
- Lower Mainland high school trades program is unique
- Construction Learning Forum aims to educate
- High schools looking for more industry participation
- Industrial construction supervisor program takes off
- Saskatchewan bill passed
- Edmonton garners support for regional cash for arena
- Feds pledge $5 million for Vimy memorial
- VIDEO: Competing in the trades
- Provinces need to loosen up apprenticeship rules
- Way Up on Westwood
- Building Up On Bayview
- Barrie Construction Association rolls with motorcycle ride for cancer
- Vimy Ridge memorial gets new visitor centre
- Minnesota Vikings unveil new multi-use stadium plan
- Proposed Ambassador Bridge twinning draws Windsor mayor’s ire
- Construction on pedestrian tunnel to Billy Bishop Airport continues to make progress
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More