CONDOMINIUM APARTMENT TOWER, COMMERCIAL Proj: 9088191-11
Abbotsford, Fraser Valley RD BC NEGOTIATED/PLANS COMPLETE
Mahogany at Mill Lake - Phase 1, 32828 Bevan Ave, across from Mill Lake, V2S
$100,000,000 est
Start: June, 2013 Complete: November, 2015
Note: The tower went through some redesign and has received approval from the City to proceed. Construction may commence by Summer 2013. The owner/bldr primarily uses invited sub trades. Phase Two is on hold and is under project #9164256.
Website: www.mahoganycondos.com.
Project:reinforced concrete foundation, steel pile foundation, cast-in-place concrete structural frame, structural steel frame, other mechanical system, package air conditioning/heat pump system, steam/hot water heating system, 02315; excavation, 02820; ornamental metal fences and gates, 02935; landscape, 04080; masonry, 08410; aluminum-framed storefronts, 08800; glazing systems, 09620; plastic laminate flooring, 09680; carpet, 11450; residential appliances, 12400; interior decorating, 13700; security access and surveillance, 13850; fire alarm, 13910; fire sprinkler, 14240; hydraulic elevators, 09650; resilient tile flooring, granite countertopss; gas range option; wood cabinetry; porcelain tile flooring; engineered hardwood flooring option; natural stone tile; radiant in-floor heating; FOB secured high-speed elevators; window wall & curtain wall exterior bldg systems; geothermal heating/cooling system; Phase One - condo tower with 156 units on floors above fourth; first three floors of CRU & office spaces; two levels u/g prkg.
Scope:300,000 square feet; 26 storeys; 2 storeys below grade; 156 units
Development:New
Category:Apartment bldgs; Retail, wholesale services
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Landscape architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Fri Aug 15, 2008. Last report Fri Aug 17, 2012.
This report Mon Mar 11, 2013.